Wednesday, October 23, 2013

Electricity – Tariff categorization and rates – Tariff Order

VERY URGENT:
e-mail and Hard copy:
TANGEDCO
(ACCOUNTS BRANCH)
144  Anna Salai,
Chennai – 600 002.

Circular Memo.No.CFC/REV/FC/REV/DFC/AAO-WI-6/D.648/2013, dt.09.10.2013.

          Sub: Electricity – Tariff categorization and rates – Tariff Order
                 dt.20.06.2013 effective from 21.06.2013 – Remarks – Reg.


          Ref: 1. Circular Memo.No.CFC/REV/FC/REV/DFC/AAO-WI-2,4,
                    dt.24.06.2013, 10.07.2013.
                 2. U.O.No.FC/REV/AAO/REV/Tariff/LT software-Ty.Sy./D.403/13,
                    dt.12.07.2013;D.461/13, dt.22.07.2013 &  e-mail to SE/IT dt.25.07.13.                  3. e-mail from AEE/LT3 to All, dt.16.07.2013 & 5.8.2013.
                 4. U.O.No.CFC/REV/FC/REV/AAO/REV/F.Tariff/D.473/13,
                    dt.29.07.2013  Lr.No.502/13, dt.5.8.2013.
                 5. U.O.No.SE/IT/EE/IT/AEE/LT.3/F.TF.revision/D.308/2013,
                    dt.06.08.2013.
                 6. Memo.No.CE/Comml/EE3/AEE1/F.Distribution Code/D.354/13,
                    dt.27.09.13.
                7.  Circular Memo.No.CFC/REV/FC/DFC/AAO-WI-5/D.636/2013,
                    dt.30.09.2013.
*****

                   In continuation with the ref.(7), the following may be adopted:
                   1.0) The Model Undertaking Format will be  arranged to be made available in the LT software.  The undertaking may be obtained from  the consumer in Rs.80/- Non-Judicial stamp paper.

2.0) The billing cycle (non-CT services – bimonthly; CT services –monthly)
is with reference to date of service connection.  For example, where the date of service connection is 10.10.2013, the billing cycle is Even Cycle in case of non-CT service.

                   3.0) In case where the undertaking is provided by the consumer to the effect that he will accept to convert the temporary supply into appropriate permanent category, then in such cases, the miscellaneous charges viz., Registration fees, service connection charges, SD, etc., applicable to that regular permanent category may be charged while effecting the temporary supply.

                   4.0) In the case of construction of building where Temporary Supply work order has already been opened, upon completion of the construction activity the respective regular category may be assigned using ‘Tariff Conversion’ module.  However, the Temporary Supply work order may be duly closed as per the procedure. (This para will override paragraph (3.d) of Circular Memo.No.636, dt.30.09.2013[under ref.(7) cited]).

                   5.0) In respect of temporary supply provided purely for temporary purpose, in the calculation of SD, the Tariff rate may be adopted to include both Energy charges and Fixed Charges.  Further, the no. of days may be adopted as 30 days in the case of CT services and 60 days in the case of  non-CT services (OR) the proposed period of use by the consumer, whichever is less.

Encl.: One Format.
                                                                    Sd xxx (11.10.2013)
                                                                            Director (Distribution)/TANGEDCO         

To
All the Chief Engineers/Distribution Regions.
Copy  to :
The Director (Finance)/TANGEDCO.
The Director (Distribution)/TANGEDCO.
The Chief Engineer/Commercial/TANGEDCO.
The Chief Engineer/Information Technology/TANGEDCO.  This is further to the   discussion between FC/Rev & AEE/LT3 on 08.10.2013, for necessary action.
          The Assessment report may be as per para (2) above.
Copy to all the Superintending Engineers/Elecy. Distn. Circles.

:FORWARDED :: BY ORDER:


Sd XXX (11.10.2013)

Chief Financial Controller/Revenue